If you’ve been wondering why Walnut Street still looks like a construction zone, don’t expect that perfectly smooth blacktop anytime soon.
Scioto County commissioners say the project is actually running a little ahead of schedule, but there’s a reason crews aren’t rushing to put down the final layer of pavement.
They want to make sure the repairs underneath have time to settle before finishing the job.
That means drivers will spend the winter traveling on a partially finished road, with the final coat of asphalt planned for next year.
Commissioner Scottie Powell warned residents Thursday that the road may not look particularly attractive for a while. But that doesn’t mean the work has stopped.
Why Crews Are Waiting
Powell said the plan is to put down enough pavement to get drivers through the winter, then return for the finishing work.
“Eventually there will be a top coat to smooth it out, but that may be a while because they want to make sure it’s not going to settle any more,” Powell said.
The concern is that putting down the final surface too soon could create problems if the repaired areas underneath continue to settle.
Instead, crews are taking a more cautious approach.
Walnut Street is expected to be partially paved before winter, with the final surface scheduled for next year.
Powell acknowledged that some residents may look at the road and think, “This looks terrible.”
But he emphasized that what drivers will see this winter isn’t the completed project.
City and County Working Together
The Walnut Street work is part of a broader effort involving cooperation between Portsmouth and Scioto County on road improvements.
Commissioner Merit Smith said several streets have already been milled as part of the arrangement.
The county and city have been coordinating projects to get better prices and stretch available road funding further.
“The city is able to do that because we’ve collaborated to come together and get a better price, so they are able to do more roads,” Smith said.
The arrangement allows Portsmouth to benefit from the county’s roadwork experience and purchasing power.
Powell also praised Scioto County Engineer Darren LeBrun for helping coordinate the projects.
He said LeBrun played an important role in getting the Scherer Hollow Road project completed and has continued helping the city with other road improvements.
“He is giving his expertise to the city to try to take care of some of the city roads, too,” Powell said.
“He doesn’t have to, but he has a heart for the community.”
Powell said LeBrun hasn’t received enough credit for his work on the projects.
Scherer Hollow Shows Why Cooperation Matters
Scherer Hollow Road, which reopened this week after being closed since August, presented an unusual challenge because portions of the roadway fall under different jurisdictions.
Powell pointed out that the road moves from city territory to county territory and back again.
That made cooperation particularly important.
The commissioners credited the partnership with helping move the project forward.
Now they’re hoping the same approach will help get more work done on Portsmouth streets.
For Walnut Street drivers, though, the immediate message is simple.
The project isn’t finished, even if the road is open to traffic.
Expect a partially paved surface this winter and the final coat sometime next year, once crews are confident the underlying repairs have settled.