Portsmouth officials are asking City Council to put another $350,000 into the Walnut Street rehabilitation project and related paving work.
The request will come up at Monday’s City Manager’s Conference.
According to the city manager’s request, construction on Walnut Street is already underway, but several issues have come up as the project progressed that require additional money.
The city also says it has an opportunity to pave U.S. 52 east from Chillicothe Street to the Waller Street underpass this year.
To cover both the additional Walnut Street work and that paving, the administration wants council to transfer and appropriate $350,000 from the city’s State Highway Fund.
The city manager is also asking council to waive the normal three-reading process so most of the work can be completed before the end of the year.
“I realize this is a significant change but I feel it is justified,” the request to council says.
Walnut Street Already Wasn’t Going to Look Finished
This is the latest development in a Walnut Street project SCDN has been following for months.
Officials previously warned that residents should not expect the street to look completely finished this winter.
The roadway was expected to receive enough paving to get it through the colder months, but the final top coat was planned for next year, allowing time for the newly reconstructed roadway and subgrade to settle before the last surface is applied.
That means drivers could see a street that is usable but still looks unfinished for months.
The city and Scioto County have also been coordinating road work in an effort to stretch paving dollars further and get better pricing on larger projects.
Walnut Street has been one of the higher-profile pieces of that work. SCDN previously reported on concerns about how long the street would remain under construction and how the partially completed pavement would look through winter.
Why Another $350,000?
The city manager’s memo does not spell out every individual problem discovered during construction.
It says only that “several issues have arisen” as the Walnut Street rehabilitation progressed and that those issues require more money.
The request also bundles in the opportunity to pave the U.S. 52 section between Chillicothe Street and the Waller Street underpass before the construction season closes.
The money would come from Fund 233, the State Highway Fund.
That fund is used for street and state-highway improvements and maintenance.
So the request is not for general city spending. It would move highway money directly into paving and rehabilitation work.
Trying to Beat Winter
The request to waive three readings is important because of the calendar.
Normally, legislation works its way through multiple readings before final action.
In this case, the administration wants council to move faster so crews can complete as much paving as possible this year, before weather shuts down asphalt work.
Council will have several choices Monday.
Members can authorize legislation transferring and appropriating the full $350,000, modify the amount or scope, take no action, or reject the request.
If council agrees to move forward and later waives the three-reading requirement, the city could get the additional money into the project much faster.
A Bigger Road-Work Push
The Walnut Street request also comes during a broader push by Portsmouth to catch up on street work.
Earlier this fall, council was asked to accept and appropriate $1.5 million in federal Community Project Funding for engineering street resurfacing work. That legislation also came with a request to waive three readings because work was already underway.
The city’s 2026 Capital Improvement Program separately included $500,000 for street resurfacing, with specific streets to be determined.
Now Walnut Street and part of U.S. 52 could get another $350,000 added to the mix.
The question for council Monday will be whether the problems uncovered on Walnut Street — plus the chance to get another section of U.S. 52 paved before winter — justify adding that much more money to the road-work tab.
And for drivers who have already spent months watching Walnut Street get torn apart and rebuilt, one thing remains unchanged:
Even with another $350,000 on the table, the street still isn’t expected to look completely finished until next year.