Portsmouth’s new City Building could need another $195,000 before the renovation is finished.
At Monday’s City Manager’s Conference, council members will be asked to consider legislation appropriating the additional money from the city’s General Fund to cover electrical and plumbing problems discovered as demolition and construction moved forward.
City Manager Sam Sutherland said the money would go toward “incidental electrical and plumbing repairs that have arisen as demo and construction has progressed.”
Council members can agree to send the request forward as legislation, modify it, take no action or reject it.
And if the request sounds familiar, there’s a reason.
The transformation of the former Fifth Third Bank building into Portsmouth’s new municipal headquarters has been getting more expensive for years.
From Building Swap to Multimillion-Dollar Project
The city’s move toward a new headquarters began when Portsmouth traded the long-vacant Marting’s Building to the Southern Ohio Port Authority in exchange for the former Fifth Third Bank building downtown.
The plan was to renovate the bank building and move city offices there.
But inflation, construction costs and the realities of renovating an existing building pushed the price upward.
SCDN previously reported that estimated renovation costs had climbed to about $4.6 million.
That eventually led City Council to approve a temporary transfer of millions of dollars from the General Fund to keep the project moving.
$4 Million Moved From General Fund
Earlier this year, council approved moving $4 million from the city’s General Fund to help finish the renovation.
That decision drew concern because the General Fund supports a wide range of city operations.
City Auditor Trent Williams stressed that the transfer was intended to be temporary, with the city planning to replace the money through the sale of municipal bonds.
At the time, Williams said final renovation expenses could potentially come in much lower, but officials wanted authority to prepare for costs in the $4 million to $4.5 million range if necessary.
Then Came the Bonds
Portsmouth later moved ahead with plans to issue as much as $4.5 million in City Building Improvement Bonds.
Those bonds could run for as long as 30 years, with the proceeds used to cover remaining renovation costs, reimburse the General Fund and pay expenses connected with issuing the debt.
The bonds are backed by the full faith and credit of the city, although officials have said they expect ordinary city revenues to cover the payments rather than relying on property taxes.
In other words, Portsmouth has already built considerable financial flexibility into the project.
Now another $195,000 is being requested.
What Went Wrong This Time?
According to Sutherland’s memo, the newest expenses involve electrical and plumbing repairs discovered during demolition and construction.
That’s not necessarily unusual when renovating an older commercial building.
Walls come down.
Ceilings open up.
Old wiring and plumbing that looked fine on paper suddenly become visible.
And occasionally the building introduces itself with a bill.
The city manager’s request does not spell out exactly what failed, how many problems were found or whether the $195,000 is expected to cover all remaining surprises.
It simply asks council to appropriate the money from General Fund line item New City Building.
Both Sutherland and city official Crystal Weghorst are expected to be available to answer council members’ questions.
Another Addition to a Long-Running Tab
The important thing is not to simply add $195,000 to every previously announced number and call that the project’s total cost.
Some of the earlier figures represented estimated costs.
Others represented money temporarily transferred from the General Fund.
And the $4.5 million bond authorization represents borrowing capacity that can be used to reimburse the city and finish the project.
But the direction of travel is pretty clear.
The city swapped for the former bank building.
Renovation costs rose.
Council moved millions out of the General Fund.
Officials prepared long-term borrowing to put the money back.
And now construction has uncovered another $195,000 worth of electrical and plumbing work.
Monday’s conference won’t be the final vote on spending the money.
Council members will first decide whether to move the request forward as legislation.
But after years of rising estimates and additional financing, the newest question surrounding Portsmouth’s future City Building is becoming a familiar one:
How much more will it cost before the doors finally open?