If Walnut Street looks unfinished this winter, that’s because it is.
Portsmouth City Manager Sam Sutherland is offering an update on the much-discussed US 52/Walnut Street rehabilitation project, confirming that the road is nearing completion but won’t get its final layer of asphalt until next year.
That matches what SCDN recently told readers as questions mounted about the project’s appearance, timeline and cost.
According to Sutherland, the city intentionally plans to leave the current intermediate asphalt course in place through the winter.
“Since this project involved extensive subgrade rehabilitation, we plan to leave the intermediate asphalt course in place through the winter and allow traffic to run over it,” Sutherland said.
The idea is to let regular traffic expose any trouble spots before crews put down the smooth final surface.
“This will give us an opportunity to identify and address any issues before placing the final surface course next year,” Sutherland said.
So, yes, drivers are currently traveling on real pavement.
No, it is not the finished product.
$1.2 Million Original Contract
Allard Construction is performing the Walnut Street work under an original contract valued at $1.2 million, funded through a combination of city money and grants.
The project has involved much more than simply grinding off old asphalt and putting down new pavement.
According to the city, crews have performed major subgrade repairs, along with curb and sidewalk work and roadway resurfacing.
Those underground repairs are a big reason the city wants to give the street a winter of traffic before applying the final surface.
Sutherland said the final asphalt course next year should provide motorists with a smoother ride.
“We appreciate the public’s patience throughout this project and look forward to getting it completed,” he said.
And More Money Could Still Be Coming
The update comes just after SCDN reported that city officials are considering another $350,000 for road work connected to Walnut Street and additional US 52 paving.
At Monday’s City Manager’s Conference, council members are expected to consider a request to transfer and appropriate $350,000 from the State Highway Fund.
The administration said additional issues arose as the Walnut Street rehabilitation progressed.
That request also includes an opportunity to pave US 52 east from Chillicothe Street to the Waller Street underpass before the end of this year.
That distinction matters.
The entire $350,000 is not necessarily being added to the Walnut Street contract alone. The request covers both additional rehabilitation needs and the extra US 52 paving opportunity.
City officials have asked council to move quickly on that funding so as much work as possible can be completed before winter shuts down the paving season.
Next Up: $5 Million for Coles Boulevard
And Walnut Street isn’t the end of Portsmouth’s major road projects.
Sutherland also announced that the Ohio Department of Transportation is preparing to bid the Coles Boulevard rehabilitation project on Dec. 17.
Construction is scheduled for next year.
The estimated price tag?
About $5 million.
And, like Walnut Street, this will be much more than a simple resurfacing job.
The Coles Boulevard project is expected to include:
- major storm sewer replacement;
- sidewalk improvements;
- traffic signal upgrades;
- roadway resurfacing;
- approximately 2,500 linear feet of new storm sewer pipe;
- more than 2,000 tons of asphalt.
The project will be financed through a combination of grant and city funds.
Portsmouth applied for grant money several years ago, and the project has remained in the design stage while officials waited for that funding to become available.
“This is a major investment in Coles Boulevard that goes well beyond resurfacing the roadway,” Sutherland said.
He said the work will address drainage problems while also improving sidewalks, signals and the road surface.
So What Happens With Walnut Street Now?
For drivers, the short version is pretty simple.
Most of the heavy work is nearing the finish line.
Traffic will continue using the intermediate pavement through winter.
The city will watch for problems as the repaired subgrade settles and takes the pounding of everyday traffic.
Then crews will return next year and apply the final surface course.
So if you drive down Walnut Street in January and think:
“Surely this isn’t finished?”
You’re right.
It isn’t.
And this time, that’s the plan.